Region Wise Projects

Pune Projects l Mumbai Projectsl Amaravati Projects l Aurangabad Projects l Nashik Projectsl Nagpur Projects l List Of Budgeted Works in Dec 2016 Under Hybrid - Annuity Model l

Pune Region Projects l Pune l Kolhapur l Sangli l Viaduct l Administrative Building Islampur l Forensic Building l Khambataki Ghat l Court Building Satara l Public School building l Sales Tax building l Eyebank Building at Satara l l Building for Hotel Management & Catering Technology l Construction of new bridge on Krishna rivers at Sangli l l Construction of Viaduct l PWD PPP Projects l

  • Nira Devghar Pune

    Pune Projects-Nira Devghar irrigation project taluka Bhor district Pune.

    Estimated Cost:- Rs.2.50 Crores
    Length Of Viaduct:- 125 m. Having 5 spans of each 25m in length
    Structural Details:- R. C. C. Circular piers with Neoprene bearing Height of pier - 25 to 30m.
    Centering:- Trusels staging

  • Pune Projects- Construction of Central Administrative building at Islampur Tal. Walwa Dist. Sangli

    Date of Start:- Dt. 24/3/2005
    Date of Completion:- Dt. 1/08/2008
    Final Cost:- Rs. 175.36 Lakh
    Total Built-up Area:- 1587.40 Squere metre.
    Number of Storeys:- Ground + Three Floor

  • Pune Projects- Construction of Forensic Science Building, Miraj, Sangli

    Brief description:- R.C.C. Framed structure (Ground + First floor)
    Date of Start:- 26/08/2008
    Date of Completion:- 20/08/2009
    Final Cost (on completion):- Rs.96.50

  • Pune Projects- Khambatki Ghat B.O.T. Project on N.H.4

    Technical Sanction Dated:- 29/12/97 for Rs. 32.00 crores.
    (Date and Amount)
    Date of Start:- 20/01/1999
    Date of Completion:- 20/08/2000
    Final Cost (on completion):- 38.00 crores

  • Pune Projects- Construction of District Court Building at Satara

    Technical Sanction:- Date 17-8-96 cost Rs.4,62,80,230/-
    (Date and Amount) Date of Start:- 30-5-97
    Date of Completion:- Date 28-11-2000 (Work in progress)
    Final Cost (on completion):- Rs.10,24,04,572/-

  • Pune Projects- Construction of Public School building for Mehetar Samaj at Yerawada

    Date of Start:- 01/01/1997
    Date of Completion:- 31/12/1998
    Final Cost (on completion):- RS. 104.67 Lac
    Number of Storeys:- Ground + 2 upper floors